Here are the ongoing activities for the next 2 weeks:
- Flooring ongoing until next Tuesday 06-20
- Ceiling tile install started this week and will be ongoing until the end of next week
- Casework & Millwork install are ongoing until 06-29
- Furniture delivery was postponed to 06-20 and the install will be ongoing for 1 week
- Fire Alarm programming and Texting is scheduled for 06-15 at 6PM (off-hours inspection by BFD)
- Certificates of Occupancy application next week for issuance on 06-30
Have a nice long weekend!