Week 152: June Updates

Construction Updates

Here are the ongoing activities for the next 2 weeks:

  • Flooring ongoing until next Tuesday 06-20
  • Ceiling tile install started this week and will be ongoing until the end of next week
  • Casework & Millwork install are ongoing until 06-29
  • Furniture delivery was postponed to 06-20 and the install will be ongoing for 1 week
  • Fire Alarm programming and Texting is scheduled for 06-15 at 6PM (off-hours inspection by BFD)
  • Certificates of Occupancy application next week for issuance on 06-30

collage of L1 spaces in the final stages of renovation

 

 

Have a nice long weekend!