Construction Updates
- Plumbing installs in Rare book area is completed
- Plumbing tie-in in LL2 Bathroom is still ongoing for the 2 upcoming weeks
- Z-Duct in the 3 classrooms is being installed starting Thursday 05-04 for a week
- Ceiling Grid & Whiteout process will start a week later followed by connection of the devices to the tiles
- Flooring is starting week of 05-08
- Casework / Millwork is targeted to start mid-May
FYI— During the second weekend of June, the ceiling cracks on the 1st floor will be repaired. Please pardon the disruption as portions of the 1st floor might be unavailable.
Graduation Tours and Upcoming Resource Fair
We are looking for volunteers to give tours during graduation week which is the week of May 22nd. Below is a link to sign up. Also, please see below information on Countway’s Resource Fair which will take place in the Fall. Reach out to Yasmina or Meredith with any questions.
Also, please note that the Coop has reserved the 1st floor classrooms from May 11th through May 31st for graduation regalia pick up and drop off. We may see increased traffic on the 1st floor during the month of May.
Happy May!
Elaine