Week 146: April Updates and Looking Ahead

Construction Updates

  • Plumbing Install Sanitary Connection LL2 is schedule starting next week for 2 weeks
  • The Duct is complete less the Drops – these will be installed after the ceilings is in
  • Painting 1st coat is starting the end of this week (04-24-2023) starting on the south side, going around the building and get to in the inside space
  • Ceiling Grid is starting the week of 05-01-2023. The install will follow the same logic as painting above
  • Architectural Finishes install process will start mid-May

construction project collage showing L1 with new drywall installed.

 

Graduation Tours and Upcoming Resource Fair

We are looking for volunteers to give tours during graduation week which is the week of May 22nd. Below is a link to sign up. Also, please see below information on Countway’s Resource Fair which will take place in the Fall. Reach out to Yasmina or Meredith with any questions.

 

Have a nice weekend.

Elaine