Construction Updates
- Plumbing Install Sanitary Connection LL2 is schedule starting next week for 2 weeks
- The Duct is complete less the Drops – these will be installed after the ceilings is in
- Painting 1st coat is starting the end of this week (04-24-2023) starting on the south side, going around the building and get to in the inside space
- Ceiling Grid is starting the week of 05-01-2023. The install will follow the same logic as painting above
- Architectural Finishes install process will start mid-May
Graduation Tours and Upcoming Resource Fair
We are looking for volunteers to give tours during graduation week which is the week of May 22nd. Below is a link to sign up. Also, please see below information on Countway’s Resource Fair which will take place in the Fall. Reach out to Yasmina or Meredith with any questions.
Have a nice weekend.
Elaine