This morning we met with GreenerU who will be installing LED Lighting Upgrades to Countway and Gordon Hall. The main takeaways of this project (specific to Countway) are listed below:
- 12/5 start date
- the project will last approx. 6 weeks
- floors L2, 2-5 are affected
- floors L1, 1, 6 are excluded
- they work from the highest floor to the lowest floor
- in the book stacks, light fixtures remain the same but will just switch to LED lighting
- in offices/corridors, new fixtures and new LED lighting will be installed
- work time is 5:30am-1:30pm
- the work is performed one floor at a time
This should not impact the L1 renovation work that is also scheduled for the beginning of December, but we will be in strong communications with HMS Facilities and Engineering & Construction for any overlap that might occur. I will keep you updated as this project unfolds and if any other information is presented.
Elaine